5 CONTINENTS CARGO NETWORK

Picture for news item 5 CONTINENTS CARGO NETWORK
Project Date: Feb 2017 – Mar 2017

G7 handled Project Management, Pier Side Cargo Receiving of below 60MT and Shipside Cargo Receiving of above 60MT, Loading unto specialized vessel bridge trailer and transport of 8 Kiln Shells from Seafront Port, Mariveles, Bataan to Eagle Cement Plant, San Ildefonso Bulacan 160 KM.

Heaviest Kiln Shel:
at 78.51 MT and 75.5 MT
Highest Kiln Shell:
at 5.06m (after removal of saddle)
Widest Kiln Shell:
at 5.38m
Transport Methodology:
Vessel Bridge
Project Duration:
34 Days of continuous transport (Day and Night)

Pierside Receiving

Shipside Receiving

Hermosa Concrete Arc – 5.19m Lowest Vertical Clearance

Eagle Cement Site