ENERGREEN CENECO BACOLOD POWER PLANT

Picture for news item ENERGREEN CENECO BACOLOD POWER PLANT
Project Date: September – November, 2014

G7 handled the transfer of 3 Generators and a Stator from an existing power house in EPZA Rosario Cavite to ENERGREEN Bacolod Plant. Generators were jacked down from a foundation height of 4 meters unto 8 axle multiaxle. Transport included barging to Bacolod, land transport to site, unloading and alignment to foundation.

Cargo Dimension:
Three (3) Units SULZER Generator L-7.0 x W-3.15 x H-3.59m
Weight: 90 MT
One (1) Generator Stator
L-3.8 x W-4.5 x H-3.43m
Location:
Bacolod City
Transport Challenge:
Foundation height of 4m
Transport method:
Used beams, stools and concrete blocks