+632 288 0713
+632 288 4087
GAC - PANAY ENERGY DEVELOPMENT CORP PEDC 3 150 MW EXPANSION PROJECT

Project Date: July 2014 – July 2016
G7 handled Project Management, Customs Clearance (BOC & DOF Processing), Transport and Unloading from start of construction on July 2014 to it’s completion on July 2016.
Heavy and Out of Gauge Cargo:
1,355 cbm 731 MT
General and Out of Gauge:
More than 120,000 RT
Cargo Containerized Cargo:
More than 350 TEU's
Location:
Brgy Ingore, Iloilo City
LP LOWER CASING L-8.40 x W-6.45 x H-3.75m 93MT

Transport Challenge: Cargo width of 6.45m thru tight and winding provincial road required Baranggay coordination.
180 MVA TRANSFORMER L-7.30 x W-3.00 x H-3.80m 94.3MT

TURBINE GENERATOR L-10.40 x W-4.3 x H-4.26m 195.9MT

Transport Challenge: Cargo weight of 195.9 MT required 14 axle line transport thru provincial bridge
32 MVA TRANSFORMER L-6.10 x W-2.50 x H-3.50m 43MT

STEAMDRUM L-14.60 x W-3.00 x H-3.80mS 100MT

DEARATOR STORAGE TANK L-8.15 x W-3.17 x H-3.40m 15.8MT